Commercial Solar Case Studies.
All the latest commercial solar projects carried out by Activ8 Solar Energies across the UK & Ireland
Commercial Solar
Case Studies.

System Size |
2009 kWp

Number of Panels |
6 379

Installation Time |
14 Weeks

System Size |
952 kWp

Number of Panels |
3 022

Installation Time |
6 Weeks

System Size |
909 kWp

Number of Panels |
1,800

Installation Time |
12 Weeks

System Size |
637 KWp

Number of Panels |
1,249

Installation Time |
8 Weeks

System Size |
795.8 kWp

Number of Panels |
1 730

Installation Time |
10 Weeks

System Size |
787 kWp

Number of Panels |
1,368

Installation Time |
5 Weeks

System Size |
772 kWp

Number of Panels |
1,734

Installation Time |
7 weeks

System Size |
732.06 kWp

Number of Panels |
1 494

Installation Time |
8 Weeks

System Size |
690 kWp

Number of Panels |
1 380

Installation Time |
8 Weeks

System Size |
678 KWp

Number of Panels |
1,170

Installation Time |
4 weeks